During the dry-docking of Montelape, the following works were carried out:

Modification of the bridge by increasing its dimensions to improve visibility. Repair of damage to the stern ramp. Repair of the bulbous bow.

Measurement, dismantling, and reassembly works of the tail shaft, as well as removal and cleaning of the controllable pitch propeller.

A new painting scheme was also applied to both the underwater hull and topside areas, replacement of zinc anodes, cleaning and refurbishment of the anchor chains and chain locker, and inspection and replacement of all sea valves.